Job Hazard Analysis: Concrete formwork

Build, brace, inspect, and strip wood and plywood forms for footings, walls, and slabs using circular saws, hammers, form ties, and steel stakes. Covers work near exposed rebar, from ladders and form walkways, and around concrete placement. Check site conditions before each shift: weather, ground condition, excavation edges, and overhead power lines.

Published 2026-10-23

A general example for this task. Your JHA should reflect your crew, equipment and site — review it with a competent person before work starts.

Steps, hazards and controls

StepHazardRiskControls
1. Unload and stage form lumber, plywood, stakes, and tiesBack strain and crushed hands lifting 4x8 plywood sheets and bundlesMedium
  • Have the supplier drop bundles close to the work area or use a forklift or telehandler to place them.
  • Carry full plywood sheets with two people; keep fingers clear of pinch points when setting down.
  • Wear leather work gloves.
Stacks tipping or sliding; tripping over scattered materialLow
  • Stack lumber on level dunnage, blocked and no higher than you can safely reach; keep stacks away from excavation edges.
  • Keep walkways clear and store stakes and ties in buckets or bins.
2. Cut form lumber and plywood with circular sawCuts and kickback from the circular sawHigh
  • Use a saw with a working lower guard that springs back; never pin or wedge the guard open.
  • Support plywood on sawhorses so the cut piece falls free and the blade does not pinch; clamp short pieces.
  • Keep both hands on the saw, stand to the side of the blade, and unplug before changing blades.
Electric shock from damaged cords in wet conditionsMedium
  • Plug tools into GFCI-protected outlets or a portable GFCI.
  • Inspect cords before use; tag out any cord with cuts, missing ground pin, or taped splices.
Flying chips and saw noiseMedium
  • Set the cutting station away from other workers.
  • Wear safety glasses and earplugs or earmuffs while cutting.
3. Set and stake footing and slab forms near rebarImpalement on protruding rebar or form stakesHigh
  • Bend over or guard all protruding rebar; use impalement-rated rebar caps or wood troughs where anyone could fall onto it.
  • Drive stakes flush or cap them; check caps every morning and replace missing ones.
Struck by hammer or sledge; hand injuries driving stakesMedium
  • Use a stake holder or puller instead of holding stakes by hand; replace hammers with loose or cracked handles.
  • Keep others out of swing range; wear safety glasses and gloves.
Cave-in or falling into a footing trenchMedium
  • Do not enter trenches 5 ft or deeper until the competent person confirms sloping, shoring, or a trench box.
  • Keep form material and spoil piles at least 2 ft back from the edge.
4. Erect, tie, and brace wall formsFalls from wall forms, form walkways, or ladders 6 ft or moreHigh
  • Install form brackets with walkways and guardrails, or use a scaffold, before working at height.
  • If guardrails are not possible, use a harness and lanyard tied to an anchor approved by the competent person.
  • Use an extension ladder that extends 3 ft above the landing and is tied off; never climb the form ties or braces.
Wall panels blowing over or falling before bracingHigh
  • Brace each panel as soon as it is stood up; do not leave unbraced panels at break or end of day.
  • Stop setting panels in high winds; keep workers out of the fall zone while lifting.
Pinched or crushed hands between panels and tiesMedium
  • Use pry bars and alignment tools, not hands, to line up panels and ties.
  • Call out before moving a panel; wear gloves.
5. Apply form release and inspect forms before the pourSkin and eye irritation from form release oilLow
  • Use a water-based release agent when available; read the SDS before use.
  • Spray low and downwind of yourself; wear chemical-resistant gloves and safety glasses.
Form blowout or collapse from missing ties, braces, or weak shoringHigh
  • Build forms to the drawings; the competent person inspects ties, braces, and shores before every pour.
  • Replace split or rotten lumber and bent ties before the pour.
6. Watch forms during concrete placementStruck by pump hose whip, chute, or failing formHigh
  • Only workers needed for the pour stay near the forms; nobody stands behind the pump hose or in the hose whip zone.
  • Assign a form watcher who yells stop if forms bulge, move, or leak; have extra braces and wedges ready.
Cement burns from wet concrete on skin or in eyesMedium
  • Keep clean water on site to rinse skin and eyes right away.
  • Wear waterproof gloves, rubber boots, and safety glasses; change wet clothes soaked with concrete.
7. Strip forms and clean upPanels or shores falling during strippingHigh
  • Strip only after the competent person confirms the concrete has reached the required strength.
  • Remove panels from the top down and keep people out of the area below.
Stepping on nails and tripping over stripped lumberMedium
  • Pull or bend nails right away and stack stripped lumber out of walkways.
  • Pick up ties, snap-tie ends, and scraps daily; wear puncture-resistant boots.

Required PPE

  • Hard hat — At all times on site.
  • ANSI Z87.1 safety glasses — At all times; add a face shield when spraying release agent overhead.
  • Leather work gloves — Handling lumber, stakes, and ties.
  • Waterproof or chemical-resistant gloves — Applying form release and during the pour.
  • Safety-toe boots, puncture-resistant — At all times; rubber boots when standing in wet concrete.
  • Hearing protection — Earplugs or earmuffs when running saws.
  • Full-body harness and lanyard — When working 6 ft or more above a lower level without guardrails.
  • High-visibility vest — When concrete trucks, pumps, or equipment are moving.

Training

  • Fall protection training per 29 CFR 1926.503 for anyone working from form walkways or at 6 ft or more.
  • Ladder safety training.
  • Hands-on training on the circular saw and power tools used.
  • Hazard communication training on form release agent and wet concrete, including where to find the SDS.
  • A competent person trained to inspect forms, shoring, and excavations before and during work.

Emergency

If a form collapses or someone falls or is impaled: stop the pour and all work, call 911 and give the site address. Do not remove an impaled object or cut rebar out of the person unless rescuers direct you. Keep the person still, control bleeding, and send someone to meet the ambulance.

Official sources

Make this JHA for your own job

Describe the task and the site. You get a JHA like this on your letterhead, in English and Spanish, with a crew sign-off sheet — preview free.

Create a JHA

General information, not legal advice. Templates and examples should be reviewed by a competent person before use. HardHat Binder is not affiliated with or endorsed by OSHA.

More carpentry & framing JHA examples