Job Hazard Analysis · Concrete
Job Hazard Analysis: Concrete pump truck operations
Truck-mounted boom pump placing ready-mix concrete for slabs, footings, walls, and elevated decks. Covers site setup, outrigger placement, boom deployment, pumping and hose handling, cleanout, and stowing. Crew: pump operator, hose handler(s), signal person, and finishers. Ready-mix trucks back up to the hopper during the pour.
Published 2026-10-23
A general example for this task. Your JHA should reflect your crew, equipment and site — review it with a competent person before work starts.
Steps, hazards and controls
1. Walk the site and plan the pump location before the truck arrives.
- Overhead power lines in the boom's reachHigh
- Pick a pump spot where the boom cannot reach within 20 ft of any power line in any direction.
- If you cannot keep 20 ft, call the utility to de-energize or insulate the lines before the pour.
- Assign a dedicated spotter whose only job is watching the boom near lines.
- Soft ground, backfill, or buried utilities under outriggersHigh
- Keep outriggers away from excavation edges, fresh backfill, manholes, and septic tanks.
- Ask the GC for locates and mark buried lines before the truck sets up.
2. Back the pump truck into position, set outriggers and cribbing, and level the truck.
- Struck by the backing pump truck or ready-mix trucksHigh
- Use a spotter in hi-vis for every backing move; the driver stops if he loses sight of the spotter.
- Check that the backup alarm works before moving.
- Cone off the truck and outrigger area to keep workers and traffic out.
- Truck tip-over from undersized outrigger pads or unlevel setupHigh
- Fully extend outriggers as the manufacturer chart requires and set them on rated pads or cribbing sized for the soil.
- Level the truck within the manufacturer limit before raising the boom.
- Pinched feet or hands under outrigger legsMedium
- Keep hands and feet clear while outriggers move; the operator confirms everyone is clear first.
3. Unfold the boom, attach the end hose, and run the pre-pour check.
- Boom contact with power lines or structuresHigh
- Raise the boom slowly with the spotter watching the lines and the operator watching the spotter.
- Keep everyone off and away from the truck while the boom moves.
- Worn pipe, clamps, or end hose bursting under pressureHigh
- Inspect pipe wear, clamps, pins, and the end hose; replace anything worn before pumping.
- Never attach anything except the end hose to the boom tip; no kinks or extra hoses beyond the manufacturer limit.
4. Prime the line and start pumping concrete.
- End hose whipping when air comes out at startup or after a blockageHigh
- Clear everyone at least the length of the end hose plus 3 ft away from it at startup and restart.
- Hose handler stays out of the whip zone until steady concrete flows.
- Keep the hopper full so the pump does not suck air.
- Hands in the hopper grate or moving valveHigh
- Keep the hopper grate in place at all times; never reach through it.
- Shut off and lock out the pump before clearing anything in the hopper.
- Noise from the pump engine and hydraulicsMedium
- Wear earplugs or earmuffs when working at the hopper or near the truck.
5. Place concrete with the end hose at the pour and move the boom between spots.
- Hose handler pulled off balance or over a deck edgeHigh
- Protect deck edges 6 ft or higher with guardrails, or tie off to an approved anchor.
- Never wrap the hose around your body or stand where the hose can push you over an edge.
- Hose handler and operator use agreed hand signals or radio; stop pumping before moving the boom.
- Wet concrete burns on skin and splashes in eyesMedium
- Wear waterproof gloves, rubber boots with pants over the top, and safety goggles.
- Wash concrete off skin right away with clean water; keep an eyewash bottle at the pour.
- Slips and trips on rebar, forms, and wet concreteMedium
- Cap exposed rebar ends and walk the path before the pour starts.
6. Clean out the line and hopper, and wash out at the designated area.
- Clean-out ball or concrete shooting out under pressureHigh
- Use water to push the clean-out ball when possible; never use compressed air unless the pump maker's procedure allows it.
- Put a catch basket on the discharge end and keep everyone clear of the outlet.
- Release all line pressure before opening any clamp.
- Caustic washout water on skin and eyesMedium
- Wash out only in the lined washout area and wear gloves and goggles.
7. Stow the boom, raise outriggers, and leave the site.
- Boom or truck contact with lines and workers while leavingHigh
- Fold the boom fully into its rest before lifting any outrigger.
- Use a spotter to guide the truck out and keep the crew clear.
- Debris and leftover concrete left on siteLow
- Pick up cribbing, cones, and hose sections; clean spills from walkways.
Required PPE
- Hard hat — At all times around the truck and under the boom.
- Safety goggles or ANSI Z87.1 safety glasses — Goggles at the hose, hopper, and washout; glasses at minimum elsewhere.
- Waterproof gloves — Nitrile or butyl when handling concrete or washout water.
- Rubber boots — Steel or composite toe, pants tucked outside the boots.
- High-visibility vest — At all times near trucks and traffic.
- Hearing protection — Earplugs or earmuffs at the hopper and near the running pump.
- Long sleeves and long pants — To keep wet concrete off skin.
- Full-body harness and lanyard — At unprotected edges 6 ft or higher without guardrails.
Training
- Pump operator trained and qualified by the employer on this make and model; ACPA certification recommended.
- Power line hazard training for operator, spotter, and crew.
- Hose handler training on whip zones, startup, and blockage procedures.
- Hand signal or radio communication training for signal persons.
- Hazard communication training on cement and concrete burns.
- Fall protection training for anyone working at deck edges.
Emergency
If the boom touches a power line: stop, do not touch the truck or anyone touching it, and keep everyone 35 ft back. Operator stays on the truck unless there is fire; then jump clear with feet together and shuffle away. Call 911 and the utility, give the site address, and give first aid only once the line is confirmed dead.
Official sources
- 29 CFR 1926.701 — Concrete and masonry — general requirementsecfr.gov
- 29 CFR 1926.600 — Motor vehicles and mechanized equipment — equipmentecfr.gov
- 29 CFR 1926.601 — Motor vehiclesecfr.gov
- 29 CFR 1926.416 — Electrical — general requirementsecfr.gov
- 29 CFR 1926.21 — Safety training and educationecfr.gov
- 29 CFR 1926.59 — Hazard communicationecfr.gov
- 29 CFR 1926.501 — Duty to have fall protectionecfr.gov
- 29 CFR 1926.28 — Personal protective equipmentecfr.gov
Make this JHA for your own job
Describe the task and the site. You get a JHA like this on your letterhead, in English and Spanish, with a crew sign-off sheet — preview free.
General information, not legal advice. Templates and examples should be reviewed by a competent person before use. HardHat Binder is not affiliated with or endorsed by OSHA.