Job Hazard Analysis · HVAC
Job Hazard Analysis: Rooftop unit replacement
Remove an existing packaged rooftop HVAC unit and set a new unit on the existing curb using a crane. Includes roof access, fall protection setup, electrical and gas lockout, refrigerant recovery, disconnecting and reconnecting gas, power, ductwork, and condensate, startup testing, and roof cleanup. Work is done outdoors on a low-slope commercial roof, often in direct sun and wind.
Published 2026-10-23
A general example for this task. Your JHA should reflect your crew, equipment and site — review it with a competent person before work starts.
Steps, hazards and controls
1. Set up roof access and fall protection
- Fall while climbing the extension ladder to the roofMedium
- Use the building's fixed roof hatch or stairs if available instead of a portable ladder.
- Extend the ladder at least 3 ft above the roof edge, set it at a 4:1 angle, and tie it off at the top.
- Keep three points of contact. Hoist tools and materials with a rope; do not carry them up the ladder.
- Fall from the unprotected roof edge (6 ft or more)High
- Set the work area away from the edge when possible. Use parapets 39 in. or higher or install guardrails at exposed edges near the work.
- Set a warning line at least 6 ft from the edge, and at least 10 ft where mechanical equipment is used, with a safety monitor for anyone working outside the line.
- Anyone working between the warning line and the edge wears a full-body harness tied to a rated anchor.
- Fall through skylights or weak roof deckingHigh
- Walk the roof before work and mark every skylight, hatch, and soft spot.
- Cover skylights with secured covers or screens that hold twice the expected load and are marked COVER.
- Never sit, step, or set tools on a skylight.
2. Shut off and lock out power and gas to the old unit
- Electric shock from the 208V–480V unit disconnect and supply wiringHigh
- Open the rooftop disconnect and the feeding breaker in the electrical room. Put your own lock and tag on each.
- Test your meter on a known live source, then verify zero voltage at the unit terminals phase-to-phase and phase-to-ground.
- Discharge capacitors with an insulated tool before touching them.
- Gas leak, fire, or explosion from the natural gas or propane lineHigh
- Close the gas cock at the unit, lock or tag it in the off position, and cap the line right after disconnecting.
- No smoking, torches, or grinders within 35 ft until the gas line is capped and checked with a gas detector or soap solution.
- Keep a charged ABC fire extinguisher on the roof.
3. Recover refrigerant from the old unit
- Frostbite or eye injury from refrigerant spray at hose connectionsMedium
- Only an EPA Section 608 certified tech connects the recovery machine.
- Use hoses with low-loss fittings and check gaskets before connecting.
- Wear safety glasses with a face shield and refrigerant-rated gloves when connecting or disconnecting hoses.
- Overpressure or rupture of the recovery cylinderMedium
- Use a DOT-rated recovery cylinder and a scale. Do not fill past 80 percent.
- Keep the cylinder upright, secured, shaded, and away from the roof edge.
- Keep the SDS for the refrigerant on site and review it with the crew.
4. Disconnect ductwork, condensate, and prep the old unit for lifting
- Cuts from sheet metal edges, screws, and unit panelsMedium
- Use a cordless screw gun and tin snips; keep blades sharp and guards in place.
- Wear cut-resistant gloves and long sleeves when handling duct and panels.
- Strains from lifting panels, curb adapters, and partsLow
- Use two people for anything over 50 lb, or lift it with the crane.
- Bend your knees and keep the load close to your body.
- Heat illness from sun and heat reflected off the roof membraneMedium
- Schedule the lift and heavy work for early morning in hot weather.
- Keep cool water on the roof, drink a cup every 15–20 minutes, and take rest breaks in shade.
- Watch each other for dizziness, headache, or confusion. Give new workers time to acclimatize.
5. Crane lift: remove the old unit and set the new unit on the curb
- Struck or crushed by a swinging or dropped unitHigh
- Use a qualified crane operator, a qualified rigger, and one designated signal person. Hold a pre-lift meeting on weights and the lift path.
- Rig only at the manufacturer's lifting points with spreader bars. Inspect slings and shackles before the lift.
- Barricade the ground below the lift path and keep everyone out. Never stand under the load.
- Use tag lines to guide the unit. Stop the lift if wind gusts make the load hard to control.
- Crane boom or load contacting overhead power linesHigh
- Survey the setup area for power lines before the crane arrives.
- Keep the boom, lines, and load at least 20 ft from lines up to 350 kV, or have the utility de-energize or cover them.
- Assign a spotter to watch clearance during the whole lift.
- Fall into the open roof curb after the old unit is removedHigh
- Set the new unit right after removing the old one to keep the opening time short.
- If the curb is left open, cover it with secured plywood marked COVER or put guardrails around it.
- Anyone guiding the unit at the open curb is tied off with a harness and lanyard.
6. Connect gas, power, ductwork, and condensate to the new unit
- Electric shock if the circuit is energized while wiringHigh
- Keep your lock and tag on the disconnect and breaker until all terminations are done and covers are on.
- Re-verify zero voltage before you start wiring.
- Gas leak at new pipe connectionsHigh
- Use thread sealant rated for gas and the correct fittings; install a drip leg and shutoff per the manufacturer.
- Leak test every joint with soap solution or a gas detector before opening the gas to the unit.
- Skin and eye irritation from duct sealant, roof adhesives, and caulkLow
- Read the SDS and container label before use.
- Wear nitrile gloves and safety glasses; keep solvent-based products away from flames.
7. Start up and test the new unit
- Shock or arc flash while testing with panels openHigh
- Only a qualified tech does live testing. Remove only the panels needed.
- Use a CAT III or CAT IV rated meter with insulated leads, and keep one hand away from the unit when possible.
- Wear voltage-rated gloves and safety glasses when testing energized parts.
- Caught in condenser fans, blower belts, and pulleysMedium
- Lock out the disconnect before adjusting belts or reaching into the blower section.
- Keep fan guards and access panels on while the unit runs. No loose sleeves, gloves near belts, or hanging cords.
- Carbon monoxide from a blocked flue or bad combustionMedium
- Check that the flue and combustion air openings are clear before firing the burner.
- Do a combustion check with an analyzer and stay upwind of the flue outlet.
8. Clean up the roof and remove fall protection
- Trips on scrap duct, screws, straps, and packagingLow
- Pick up scrap as you go and put it in a bin or tied bundle.
- Pick up screws and sharp pieces with a magnet sweeper.
- Falling debris striking people below; wind blowing loose material off the roofMedium
- Never throw material off the roof. Lower it with the crane, a hoist, or an enclosed chute to a barricaded area.
- Weigh down or tie off packaging and sheet goods in wind.
- Fall from the edge while taking down warning lines and guardrailsMedium
- Take down edge protection last, after all other work is done.
- Stay tied off while removing guardrails at the edge.
Required PPE
- Hard hat — ANSI Z89.1 hard hat at all times during the crane lift and on the ground near the roof.
- Safety glasses — ANSI Z87.1 safety glasses at all times.
- Face shield — Over safety glasses when connecting refrigerant hoses or cutting metal.
- Cut-resistant gloves — When handling sheet metal, duct, and unit panels.
- Refrigerant and voltage-rated gloves — Refrigerant-rated gloves for hose work; voltage-rated gloves for live electrical testing.
- Full-body harness and lanyard — For anyone working outside the warning line or at an open curb. Inspect before each use.
- Safety-toe work boots — Slip-resistant soles at all times on the roof.
- High-visibility vest — During the crane lift and in ground-level barricaded areas.
- Hearing protection — Earplugs or earmuffs near the running crane or when cutting with power saws.
Training
- Fall protection training per 29 CFR 1926.503, including warning lines, hole covers, and harness use.
- EPA Section 608 certification for anyone handling refrigerant.
- Certified or qualified crane operator, qualified rigger, and qualified signal person for the lift.
- Lockout/tagout training for electrical disconnects and gas shutoffs.
- Ladder safety training.
- Hazard communication training on refrigerants, sealants, and adhesives used on this job.
- Heat illness recognition and first aid.
Emergency
If someone falls or is struck by the load: stop all work and stop the crane. Call 911 and give the site address and the roof access point. Do not move the injured worker unless they are in danger. Give first aid until help arrives. If a worker is hanging in a harness, rescue them right away to prevent suspension trauma.
Official sources
- 29 CFR 1926.501 — Duty to have fall protectionecfr.gov
- 29 CFR 1926.502 — Fall protection systems criteria and practicesecfr.gov
- 29 CFR 1926.503 — Fall protection training requirementsecfr.gov
- 29 CFR 1926.1053 — Laddersecfr.gov
- 29 CFR 1926.416 — Electrical — general requirementsecfr.gov
- 29 CFR 1926.417 — Lockout and tagging of circuitsecfr.gov
- 29 CFR 1926.59 — Hazard communicationecfr.gov
- OSHA — Heat — hazard recognition and preventionosha.gov
Make this JHA for your own job
Describe the task and the site. You get a JHA like this on your letterhead, in English and Spanish, with a crew sign-off sheet — preview free.
General information, not legal advice. Templates and examples should be reviewed by a competent person before use. HardHat Binder is not affiliated with or endorsed by OSHA.