Job Hazard Analysis · Masonry
Job Hazard Analysis: Brick veneer installation
Laying full-size clay brick veneer over sheathed wood or steel stud walls on new or existing buildings. Includes frame scaffold setup, staging brick and mortar, mixing mortar in a powered mixer, cutting brick with a wet masonry saw, setting wall ties and flashing, tooling joints, cleaning brick with acid cleaner, and teardown. Work is outdoors and exposed to weather.
Published 2026-10-23
A general example for this task. Your JHA should reflect your crew, equipment and site — review it with a competent person before work starts.
Steps, hazards and controls
1. Set up the work area and erect the frame scaffold
- Scaffold collapse from soft ground, missing base plates, or missing bracesHigh
- The competent person picks the scaffold location and checks the ground before erection.
- Set every leg on base plates and mudsills; level with screw jacks, never with brick or block.
- Install all cross braces and tie the scaffold to the building when it is more than 4 times taller than its base width.
- Competent person inspects the scaffold before each shift and tags it before anyone climbs.
- Falls while erecting upper lifts of scaffoldHigh
- Plank each level fully before climbing to the next.
- Climb only on built-in ladders or attached ladders, never on cross braces.
- Use guardrails or a harness tied to a proper anchor as set by the competent person.
- Struck by dropped frames, planks, or pinsMedium
- Barricade the area below with caution tape or cones while erecting.
- Pass components hand to hand or hoist with a rope; do not throw them.
- Wear a hard hat inside the barricaded zone.
2. Stage brick, sand, and mortar bags
- Struck by rough-terrain forklift moving brick cubesHigh
- Set a marked travel path for the forklift away from where the crew works.
- Only trained, authorized operators drive the forklift; use a spotter near the scaffold.
- Stay out of the swing and travel path and make eye contact with the operator. Wear a high-visibility vest.
- Overloading scaffold planks with brick and mortarHigh
- Competent person states the load limit; keep brick stacks small and spread out over the frames.
- Do not set mortar boards or brick in the middle of a plank span.
- Back and shoulder strain from lifting brick and 80-lb mortar bagsMedium
- Have the forklift set pallets close to the mixer and the scaffold.
- Use brick tongs and a wheelbarrow or cart; two-person lift for full bags.
- Lift with your legs, keep the load close, and do not twist.
3. Mix mortar in the power mixer
- Caught in rotating mixer paddlesHigh
- Keep the grate guard on the mixer at all times.
- Never reach into the drum or poke it with a shovel while it turns; shut it off first.
- No loose sleeves, gloves with cuffs hanging, or drawstrings near the mixer.
- Cement and silica dust when dumping bagsMedium
- Set the mixer so wind blows dust away from the operator and the crew.
- Slit bags low over the drum and pour slowly; add water first.
- Wear safety glasses and an N95 respirator when dumping bags.
- Skin burns from wet mortarMedium
- Keep clean water and soap at the mixer for washing skin.
- Wear nitrile-coated gloves and long sleeves; wash mortar off skin right away.
4. Cut brick with the wet masonry saw
- Respirable crystalline silica dust from cutting brickHigh
- Plan layout to cut as few brick as possible.
- Use only a saw with water feed running; never dry cut.
- Set the saw outdoors, away from other workers, and follow the company silica control plan.
- Cuts or kickback from the saw bladeHigh
- Keep the blade guard in place and use the right diamond blade for brick.
- Hold brick on the sliding tray; keep hands clear of the blade line.
- Unplug the saw before changing blades or clearing jams.
- Electric shock from saw cord in wet conditionsMedium
- Plug the saw into a GFCI outlet or GFCI cord.
- Inspect the cord daily; take damaged cords out of service.
- Loud saw noiseMedium
- Set the saw away from where others work.
- Wear earplugs or earmuffs while cutting.
5. Lay brick, set wall ties, and install flashing from the scaffold
- Falls from the scaffold work platformHigh
- Fully plank platforms and keep them within 14 inches of the wall.
- Keep guardrails on all open sides above 10 ft; never remove them to pass material.
- Do not stand on brick stacks, buckets, or ladders on the platform.
- Falling brick, mortar, or tools striking workers belowMedium
- Install toeboards or debris netting on the scaffold.
- Set a limited access zone below the wall and keep it barricaded.
- Wear a hard hat at all times around the scaffold.
- Wall collapse of fresh brick in high windMedium
- Set wall ties at the spacing on the plans as you go.
- Stop laying and keep clear of fresh, unbraced work when winds are high.
- Heat illness during summer workMedium
- Schedule heavy work in the morning and provide shade near the mixer.
- Drink water every 15 minutes and take rest breaks in the shade; new workers build up time in the heat.
- Watch each other for dizziness, confusion, or stopping sweating.
6. Tool joints and clean brick with acid cleaner
- Chemical burns to eyes and skin from muriatic acid or masonry cleanerHigh
- Use a milder detergent-type masonry cleaner instead of muriatic acid when the brick maker allows.
- Read the SDS; always add acid to water, never water to acid; use a low-pressure sprayer.
- Keep an eyewash bottle and clean water at the work area.
- Wear chemical goggles, face shield, and chemical-resistant gloves.
- Breathing acid vaporsMedium
- Work upwind and keep other workers out of the spray area.
7. Clean up and dismantle the scaffold
- Falls while dismantling scaffoldHigh
- Competent person directs teardown from the top down.
- Remove ties and braces only from the level being taken down.
- Use fall protection as set by the competent person.
- Silica dust from dry sweeping mortar and brick debrisMedium
- Wet down debris or use a HEPA vacuum; no dry sweeping or compressed air.
- Trips and cuts from broken brick, banding, and loose planksLow
- Cut banding and bin it right away; keep walkways clear all day.
- Stack scaffold parts and planks flat in a marked area.
- Wear leather gloves and safety boots.
Required PPE
- Hard hat — At all times on and around the scaffold.
- Safety glasses — ANSI Z87.1 with side shields at all times.
- Chemical goggles and face shield — When mixing or spraying acid cleaner.
- Gloves — Nitrile-coated for mortar; leather for handling brick and scaffold; chemical-resistant for acid.
- Respirator — N95 or better when dumping mortar bags; as required by the silica plan when cutting.
- Hearing protection — Earplugs or earmuffs when running the saw or near the mixer.
- Safety boots — Protective toe, slip-resistant soles.
- High-visibility vest — When forklifts or trucks are moving on site.
- Long sleeves and pants — To protect skin from wet mortar and acid.
Training
- Scaffold user training for all workers; erection and teardown only under a trained competent person.
- Silica hazard training and the company written silica exposure control plan.
- Hazard communication training on cement, mortar, and acid cleaner SDS.
- Forklift operator training and authorization for anyone driving the forklift.
- Respirator fit test and medical clearance for workers who wear tight-fitting respirators.
- Heat illness recognition and first aid.
Emergency
If someone falls from the scaffold: stop all work, do not move the injured worker unless in danger, call 911 and give the site address, send a worker to meet the ambulance, and give first aid until help arrives. For acid in the eyes, flush with clean water for at least 15 minutes.
Official sources
- 29 CFR 1926.451 — Scaffolds — general requirementsecfr.gov
- 29 CFR 1926.1153 — Respirable crystalline silicaecfr.gov
- 29 CFR 1926.706 — Requirements for masonry constructionecfr.gov
- 29 CFR 1926.701 — Concrete and masonry — general requirementsecfr.gov
- 29 CFR 1926.59 — Hazard communicationecfr.gov
- 29 CFR 1926.250 — Materials storageecfr.gov
- 29 CFR 1926.102 — Eye and face protectionecfr.gov
- OSHA — Heat — hazard recognition and preventionosha.gov
Make this JHA for your own job
Describe the task and the site. You get a JHA like this on your letterhead, in English and Spanish, with a crew sign-off sheet — preview free.
General information, not legal advice. Templates and examples should be reviewed by a competent person before use. HardHat Binder is not affiliated with or endorsed by OSHA.