Job Hazard Analysis · Masonry
Job Hazard Analysis: Scaffold erection
Masonry crew erecting a frame-and-brace (welded tubular) supported scaffold along a building wall to lay brick or block. Covers site check, base setup, erecting each lift, planking, guardrails, ties, access, inspection, and cleanup. Erection is supervised by a competent person and follows the scaffold manufacturer's instructions.
Published 2026-10-23
A general example for this task. Your JHA should reflect your crew, equipment and site — review it with a competent person before work starts.
Steps, hazards and controls
1. Plan the layout and inspect the site and all scaffold parts
- Contact with overhead power lines while raising frames or planksHigh
- Look up and locate all overhead lines before setting the first frame.
- If the scaffold will come within 10 ft of a line, call the utility to de-energize, move, or cover it first.
- Assign a spotter whenever frames or planks are carried or raised near a line.
- Damaged or mismatched frames, braces, pins, or planks causing collapseMedium
- Inspect every frame, brace, coupling pin, and plank before use; look for bends, cracks, rust, and split wood.
- Tag damaged parts 'Do Not Use' and set them aside.
- Do not mix parts from different manufacturers unless the competent person approves.
2. Unload and stage scaffold materials
- Back and shoulder strain lifting 40–60 lb frames and planksMedium
- Use a forklift or telehandler to unload bundles when available.
- Carry frames and long planks with two workers.
- Stage material close to where each section goes up to shorten carries.
- Struck by vehicles or falling bundles in the staging areaMedium
- Barricade the unloading area and post signs.
- Stack frames and planks flat on level ground, cross-stacked and not too high.
- Stay out from under suspended loads.
- Pinched fingers when stacking or handling bracesLow
- Keep hands off the ends and contact points when setting parts down.
- Wear work gloves.
3. Set the base: mudsills, base plates, screw jacks, and level the first lift
- Scaffold settling or collapsing on soft, frozen, or uneven groundHigh
- Set base plates on full mudsills (solid wood pads) on compacted, level ground.
- Never use bricks, block, or loose shims to level the scaffold; use screw jacks within the manufacturer's extension limit.
- Check plumb and level with a level before going up.
- Keep the base away from trench edges and freshly backfilled soil.
- Hand injuries adjusting screw jacks and base platesLow
- Keep fingers clear of threads and the frame leg when lowering.
- Wear work gloves.
4. Erect frames and cross braces lift by lift
- Falls from the scaffold while erecting upper liftsHigh
- The competent person decides how erectors are protected and checks it before work starts.
- Fully plank the lift you are standing on before raising the next frames.
- Wear a full-body harness and tie off to an anchor the competent person approves when it is feasible.
- Never climb cross braces; use the built-in or attached ladder.
- Frames, braces, pins, or tools dropped on workers belowHigh
- Barricade the area below and keep everyone not erecting out of it.
- Raise parts with a hand line or gin wheel, not by tossing.
- Wear a hard hat at all times.
- Partly built scaffold tipping in high wind or stormsMedium
- Stop erecting during high wind, storms, or lightning, and come down.
- Install cross braces on each frame as soon as it is set, and lock all pins.
5. Install planks, guardrails, toeboards, and access ladder
- Falls through gaps or off open sides and ends of the platformHigh
- Plank the full width of each working level with no wide gaps between planks or at the wall.
- Install top rails at 38–45 in, midrails, and toeboards on all open sides and ends 10 ft or higher.
- Install the access ladder or stair as the scaffold goes up.
- Planks sliding, tipping, or breakingMedium
- Use only scaffold-grade planks or manufacturer decks.
- Extend planks 6 to 12 in past supports, cleat or hook them, and overlap at least 12 in over a support.
- Never use a plank that is split, warped, or covered with dried mortar.
6. Tie the scaffold to the building and set outriggers if needed
- Scaffold tipping over from missing ties or heavy brick and block loadsHigh
- Install ties to the structure at the spacing in the manufacturer's instructions once height is more than 4 times the base width.
- Tie only to solid structure, never to windows, pipes, or fresh masonry.
- Do not remove ties until the scaffold above is taken down.
- Silica dust when drilling masonry for tie anchorsMedium
- Use a hammer drill with a dust shroud and HEPA vacuum.
- Wear a respirator if dust controls are not available.
7. Inspect and tag the scaffold before use and each shift
- Crew using an incomplete or overloaded scaffoldMedium
- The competent person inspects before each shift and after any storm or impact.
- Hang a green tag when ready and a red tag when not; no one climbs a red-tagged scaffold.
- Know the platform load rating; stack brick, block, and mortar tubs over the frames, not mid-span.
8. Clean up the area and secure leftover materials
- Trips over loose pins, straps, and debris around the baseLow
- Pick up pins, clips, and scraps and keep walkways clear.
- Stack spare frames and planks in a marked storage area.
- Tools or debris left on platforms falling laterMedium
- Clear tools and loose items off every platform before leaving.
- Keep barricades in place until the scaffold is tagged green.
Required PPE
- Hard hat — At all times on and around the scaffold.
- Safety glasses — ANSI Z87.1 at all times; add a face shield when drilling.
- Work gloves — Leather or cut-resistant when handling frames, braces, and planks.
- Safety-toe boots — Slip-resistant soles; at all times.
- Full-body harness with shock-absorbing lanyard — When the competent person says tie-off is feasible during erection; inspect before each use.
- High-visibility vest — During unloading and near vehicle or equipment traffic.
- Respirator and hearing protection — N95 or better and earplugs when drilling masonry for tie anchors without full dust controls.
Training
- Scaffold erector training by a qualified person: erection sequence, hazards, fall and falling-object protection, and load ratings.
- A competent person on site to supervise erection and inspect the scaffold.
- Fall protection training, including harness inspection and fitting.
- Forklift or telehandler operator training if used to unload or lift materials.
- Site hazard briefing on power lines, weather, and emergency procedures.
Emergency
If a worker falls or the scaffold collapses: stop all work, call 911 and give the site address, and do not move the injured worker unless they are in more danger. Give first aid until help arrives. If a worker is hanging in a harness, rescue them right away—suspension can become deadly within minutes.
Official sources
- 29 CFR 1926.451 — Scaffolds — general requirementsecfr.gov
- 29 CFR 1926.502 — Fall protection systems criteria and practicesecfr.gov
- 29 CFR 1926.501 — Duty to have fall protectionecfr.gov
- 29 CFR 1926.21 — Safety training and educationecfr.gov
- 29 CFR 1926.100 — Head protectionecfr.gov
- 29 CFR 1926.250 — Materials storageecfr.gov
- 29 CFR 1926.1153 — Respirable crystalline silicaecfr.gov
- 29 CFR 1926.20 — General safety and health provisionsecfr.gov
Make this JHA for your own job
Describe the task and the site. You get a JHA like this on your letterhead, in English and Spanish, with a crew sign-off sheet — preview free.
General information, not legal advice. Templates and examples should be reviewed by a competent person before use. HardHat Binder is not affiliated with or endorsed by OSHA.