Job Hazard Analysis: Scaffold erection

Masonry crew erecting a frame-and-brace (welded tubular) supported scaffold along a building wall to lay brick or block. Covers site check, base setup, erecting each lift, planking, guardrails, ties, access, inspection, and cleanup. Erection is supervised by a competent person and follows the scaffold manufacturer's instructions.

Published 2026-10-23

A general example for this task. Your JHA should reflect your crew, equipment and site — review it with a competent person before work starts.

Steps, hazards and controls

  1. 1. Plan the layout and inspect the site and all scaffold parts

    • Contact with overhead power lines while raising frames or planksHigh
      • Look up and locate all overhead lines before setting the first frame.
      • If the scaffold will come within 10 ft of a line, call the utility to de-energize, move, or cover it first.
      • Assign a spotter whenever frames or planks are carried or raised near a line.
    • Damaged or mismatched frames, braces, pins, or planks causing collapseMedium
      • Inspect every frame, brace, coupling pin, and plank before use; look for bends, cracks, rust, and split wood.
      • Tag damaged parts 'Do Not Use' and set them aside.
      • Do not mix parts from different manufacturers unless the competent person approves.
  2. 2. Unload and stage scaffold materials

    • Back and shoulder strain lifting 40–60 lb frames and planksMedium
      • Use a forklift or telehandler to unload bundles when available.
      • Carry frames and long planks with two workers.
      • Stage material close to where each section goes up to shorten carries.
    • Struck by vehicles or falling bundles in the staging areaMedium
      • Barricade the unloading area and post signs.
      • Stack frames and planks flat on level ground, cross-stacked and not too high.
      • Stay out from under suspended loads.
    • Pinched fingers when stacking or handling bracesLow
      • Keep hands off the ends and contact points when setting parts down.
      • Wear work gloves.
  3. 3. Set the base: mudsills, base plates, screw jacks, and level the first lift

    • Scaffold settling or collapsing on soft, frozen, or uneven groundHigh
      • Set base plates on full mudsills (solid wood pads) on compacted, level ground.
      • Never use bricks, block, or loose shims to level the scaffold; use screw jacks within the manufacturer's extension limit.
      • Check plumb and level with a level before going up.
      • Keep the base away from trench edges and freshly backfilled soil.
    • Hand injuries adjusting screw jacks and base platesLow
      • Keep fingers clear of threads and the frame leg when lowering.
      • Wear work gloves.
  4. 4. Erect frames and cross braces lift by lift

    • Falls from the scaffold while erecting upper liftsHigh
      • The competent person decides how erectors are protected and checks it before work starts.
      • Fully plank the lift you are standing on before raising the next frames.
      • Wear a full-body harness and tie off to an anchor the competent person approves when it is feasible.
      • Never climb cross braces; use the built-in or attached ladder.
    • Frames, braces, pins, or tools dropped on workers belowHigh
      • Barricade the area below and keep everyone not erecting out of it.
      • Raise parts with a hand line or gin wheel, not by tossing.
      • Wear a hard hat at all times.
    • Partly built scaffold tipping in high wind or stormsMedium
      • Stop erecting during high wind, storms, or lightning, and come down.
      • Install cross braces on each frame as soon as it is set, and lock all pins.
  5. 5. Install planks, guardrails, toeboards, and access ladder

    • Falls through gaps or off open sides and ends of the platformHigh
      • Plank the full width of each working level with no wide gaps between planks or at the wall.
      • Install top rails at 38–45 in, midrails, and toeboards on all open sides and ends 10 ft or higher.
      • Install the access ladder or stair as the scaffold goes up.
    • Planks sliding, tipping, or breakingMedium
      • Use only scaffold-grade planks or manufacturer decks.
      • Extend planks 6 to 12 in past supports, cleat or hook them, and overlap at least 12 in over a support.
      • Never use a plank that is split, warped, or covered with dried mortar.
  6. 6. Tie the scaffold to the building and set outriggers if needed

    • Scaffold tipping over from missing ties or heavy brick and block loadsHigh
      • Install ties to the structure at the spacing in the manufacturer's instructions once height is more than 4 times the base width.
      • Tie only to solid structure, never to windows, pipes, or fresh masonry.
      • Do not remove ties until the scaffold above is taken down.
    • Silica dust when drilling masonry for tie anchorsMedium
      • Use a hammer drill with a dust shroud and HEPA vacuum.
      • Wear a respirator if dust controls are not available.
  7. 7. Inspect and tag the scaffold before use and each shift

    • Crew using an incomplete or overloaded scaffoldMedium
      • The competent person inspects before each shift and after any storm or impact.
      • Hang a green tag when ready and a red tag when not; no one climbs a red-tagged scaffold.
      • Know the platform load rating; stack brick, block, and mortar tubs over the frames, not mid-span.
  8. 8. Clean up the area and secure leftover materials

    • Trips over loose pins, straps, and debris around the baseLow
      • Pick up pins, clips, and scraps and keep walkways clear.
      • Stack spare frames and planks in a marked storage area.
    • Tools or debris left on platforms falling laterMedium
      • Clear tools and loose items off every platform before leaving.
      • Keep barricades in place until the scaffold is tagged green.

Required PPE

  • Hard hat — At all times on and around the scaffold.
  • Safety glasses — ANSI Z87.1 at all times; add a face shield when drilling.
  • Work gloves — Leather or cut-resistant when handling frames, braces, and planks.
  • Safety-toe boots — Slip-resistant soles; at all times.
  • Full-body harness with shock-absorbing lanyard — When the competent person says tie-off is feasible during erection; inspect before each use.
  • High-visibility vest — During unloading and near vehicle or equipment traffic.
  • Respirator and hearing protection — N95 or better and earplugs when drilling masonry for tie anchors without full dust controls.

Training

  • Scaffold erector training by a qualified person: erection sequence, hazards, fall and falling-object protection, and load ratings.
  • A competent person on site to supervise erection and inspect the scaffold.
  • Fall protection training, including harness inspection and fitting.
  • Forklift or telehandler operator training if used to unload or lift materials.
  • Site hazard briefing on power lines, weather, and emergency procedures.

Emergency

If a worker falls or the scaffold collapses: stop all work, call 911 and give the site address, and do not move the injured worker unless they are in more danger. Give first aid until help arrives. If a worker is hanging in a harness, rescue them right away—suspension can become deadly within minutes.