Job Hazard Analysis · Electrical
Job Hazard Analysis: Troubleshooting circuits
Finding and fixing faults in branch circuits, feeders, panels, receptacles, switches, and fixtures up to 480V in occupied or under-construction buildings. Includes voltage testing, de-energizing and locking out, opening panels and boxes, and restoring power. Live work is limited to testing and measuring only.
Published 2026-10-23
A general example for this task. Your JHA should reflect your crew, equipment and site — review it with a competent person before work starts.
Steps, hazards and controls
| Step | Hazard | Risk | Controls |
|---|---|---|---|
| 1. Plan the job: talk to the customer, review panel schedules and drawings, and decide what can be shut off. | Wrong circuit identified because panel directory is missing or wrong, leading to contact with energized conductors. | High |
|
| Shutting off power to critical loads (medical equipment, fire alarm, refrigeration, elevators) without warning. | Medium |
| |
| 2. Set up the work area: barricade the panel or box, set up the ladder, and check your meter and tools. | Damaged or wrong-rated multimeter or test leads failing during a voltage test and causing an arc blast. | High |
|
| Falls from a 6-ft fiberglass stepladder while reaching fixtures or ceiling boxes. | Medium |
| |
| Customers or other trades walking into an open panel or work area. | Medium |
| |
| 3. Test the live circuit to find the fault: measure voltage, check breakers, and look for heat or damage. | Electric shock from touching energized bus bars, lugs, or terminals inside a 120/240V or 277/480V panel. | High |
|
| Arc flash from a slipped probe shorting phase to phase or phase to ground. | High |
| |
| Burns from overheated conductors, breakers, or failed connections. | Medium |
| |
| 4. De-energize and lock out the circuit, then verify zero voltage. | Someone re-energizes the circuit while you are working on it. | High |
|
| Backfeed or a second source (multi-wire branch circuit, generator, solar, shared neutral) keeps the circuit live. | High |
| |
| 5. Repair the fault: replace breakers, devices, splices, or damaged wire with the circuit locked out. | Cuts from utility knives, wire strippers, and sharp box edges. | Low |
|
| Striking a hidden live conductor when drilling or cutting into walls to trace wiring. | Medium |
| |
| Dust and debris falling in your eyes when working overhead in ceilings. | Low |
| |
| 6. Restore power: remove tools, reinstall covers, remove locks, and test the circuit. | Energizing with a worker still in contact, tools left in the panel, or a fault still present, causing shock or arc flash. | High |
|
| 7. Clean up: pick up wire scraps and packaging, fold the ladder, and close up the work area. | Slips and trips over wire scraps, cords, and tools on the floor. | Low |
|
Required PPE
- Safety glasses — ANSI Z87.1 at all times on site.
- Voltage-rated rubber gloves with leather protectors — Class matched to the voltage; air-test before each use. Required for testing inside panels.
- Arc-rated shirt, pants, and face shield or hood — Rated at or above the incident energy on the equipment label, for any live testing in panels.
- Hard hat — Class E electrical-rated when working on active construction sites or overhead hazards.
- Work boots — Electrical hazard (EH) rated, closed toe.
- Cut-resistant work gloves — For stripping wire and handling boxes when the circuit is locked out.
Training
- Qualified electrician training on electrical hazards, safe testing, and limits of approach before any live testing.
- Lockout/tagout procedure training, including live-dead-live testing.
- Arc flash PPE selection, inspection, and use, including rubber glove air testing.
- Ladder safety training.
- At least one crew member trained in CPR, AED use, and first aid.
Emergency
If someone is shocked: do not touch them. Shut off the power at the breaker or push them free with a dry non-conductive object. Call 911 and give the site address. Start CPR and use an AED if they are not breathing. Anyone shocked goes to the hospital, even if they feel fine.
Official sources
- 29 CFR 1926.416 — Electrical — general requirements
- 29 CFR 1926.417 — Lockout and tagging of circuits
- 29 CFR 1926.404 — Wiring design and protection
- 29 CFR 1926.405 — Wiring methods, components, and equipment
- 29 CFR 1926.95 — Criteria for personal protective equipment
- 29 CFR 1926.1053 — Ladders
- 29 CFR 1926.21 — Safety training and education
- 29 CFR 1926.50 — Medical services and first aid
Make this JHA for your own job
Describe the task and the site. You get a JHA like this on your letterhead, in English and Spanish, with a crew sign-off sheet — preview free.
Create a JHAGeneral information, not legal advice. Templates and examples should be reviewed by a competent person before use. HardHat Binder is not affiliated with or endorsed by OSHA.