Job Hazard Analysis · Roofing
Job Hazard Analysis: Roof tear-off
Removing existing asphalt shingles, underlayment, drip edge, and flashing from a steep-slope residential roof down to the wood deck. Debris goes into a dumpster or trailer on the ground. Covers setup, roof access, tear-off, debris disposal, deck check, dry-in, and ground cleanup. Weather, roof height, slope, nearby power lines, and deck condition must be checked by the competent person before work starts.
Published 2026-10-23
A general example for this task. Your JHA should reflect your crew, equipment and site — review it with a competent person before work starts.
Steps, hazards and controls
1. Set up the site: place the dumpster, tarp the ground, and protect windows and landscaping.
- Struck by the roll-off truck or a backing vehicle while placing the dumpster.Medium
- Keep workers out of the truck's path until the dumpster is set and the truck has left.
- Use one spotter in view of the driver for all backing.
- Wear a high-visibility vest near moving vehicles.
- Overhead power lines near the roof edge, dumpster, or ladder location.High
- Locate all overhead lines before setup and keep ladders, tools, and debris at least 10 ft away.
- If work must be closer, call the utility to de-energize or cover the lines before starting.
- Use fiberglass ladders only; no aluminum ladders on this job.
2. Set up roof access and install fall protection: extension ladder, roof anchors, lifelines, and roof brackets.
- Fall from the extension ladder while climbing or getting on and off the roof.High
- Set the ladder at a 4-to-1 angle on firm, level ground and extend it 3 ft above the roof edge.
- Tie off the top of the ladder and inspect rungs, feet, and locks before use.
- Keep 3 points of contact; haul tools and bundles up with a rope or ladder hoist, not in your hands.
- Fall from the roof edge while installing anchors before anyone is tied off.High
- Install the first anchor at the ridge from the ladder or from a secured position, working away from the edge.
- Nail anchors into rafters or trusses with the nails the manufacturer specifies, not just into the deck.
- Competent person checks every anchor, rope grab, and lanyard before the crew goes up.
3. Tear off shingles and underlayment with roofing shovels, working from the ridge down.
- Slipping on loose shingles, granules, or wet felt and falling off the roof.High
- Stay tied off to the lifeline with a full-body harness at all times on the roof.
- Keep lifelines short enough that you cannot reach the edge or hit the ground in a fall.
- Install roof brackets with 2x planks as toe boards on steep pitches and below the work.
- Stop tear-off when the roof is wet, icy, or in high wind.
- Falling through skylights, chimney openings, or rotten decking.High
- Cover skylights and openings with secured plywood marked HOLE or COVER before tear-off.
- Walk on rafter lines and test soft spots before putting full weight on them.
- Back and shoulder strain from prying and carrying heavy debris.Medium
- Rotate shovel and carrying jobs among the crew every hour.
- Keep loads small; do not stack debris piles on the roof.
- Cuts and punctures from exposed nails and sharp flashing.Medium
- Pull or hammer down nails as you go so the deck stays clear.
- Wear cut-resistant gloves and boots with puncture-resistant soles.
4. Drop debris into the dumpster or trailer.
- Workers on the ground struck by falling shingles, nails, or tools.High
- Park the dumpster right under the drop point or use an enclosed chute.
- Barricade and sign the drop zone; no one enters while debris is coming down.
- Call out before every drop and get an answer from the ground.
- Wear a hard hat on the ground at all times.
- Leaning over the edge to throw debris and losing balance.High
- Stay tied off and do not lean past the edge; slide debris off from behind a toe board.
5. Inspect the deck, replace damaged plywood, and dry in with underlayment.
- Kickback and cuts from the circular saw when cutting out bad decking.Medium
- Check the blade guard and cord before use; set blade depth to the plywood thickness.
- Plug into a GFCI-protected cord and keep cords away from your feet and the edge.
- Wear safety glasses while cutting and nailing.
- Nail gun injuries from contact-trip firing or double fires.Medium
- Use sequential-trigger nail guns and keep your free hand at least 12 in from the nose.
- Disconnect the air hose before clearing jams or moving the gun.
- Wind catching underlayment rolls or plywood sheets and pulling you off balance.Medium
- Carry full sheets with two people and stop handling sheets in gusty wind.
- Tear off only as much as you can dry in the same day.
6. Work in heat: plan water, rest, and shade for the whole shift.
- Heat exhaustion or heat stroke from sun and hot roof surfaces.High
- Start early and schedule the hardest tear-off before the hottest part of the day.
- Provide cool water and shaded breaks; drink a cup every 15–20 minutes.
- Let new or returning workers build up to full workloads over the first days.
- Watch each other for dizziness, confusion, or stopped sweating and report it right away.
7. Clean up: remove fall protection last, sweep for nails, and close the dumpster area.
- Falling while removing anchors and lifelines at the end of the day.High
- Take down anchors last, working from the ladder or while tied off to another anchor.
- Puncture wounds from loose nails in the yard and driveway.Low
- Run a magnetic sweeper over the yard, driveway, and drop zone twice.
- Keep walkways clear of debris and cords during the shift.
Required PPE
- Full-body harness with lanyard or rope grab — On the roof at all times; inspect before each use.
- Hard hat — For ground crew and anyone in the drop zone.
- ANSI Z87.1 safety glasses — At all times during tear-off, cutting, and nailing.
- Cut-resistant work gloves — When handling shingles, flashing, and debris.
- Roofing boots with soft, puncture-resistant soles — For grip on the roof and protection from nails.
- High-visibility vest — For ground crew near trucks and the driveway.
- Hearing protection (earplugs) — When running saws, compressors, or nail guns.
Training
- Fall protection training: harness fit, anchors, lifelines, and recognizing fall hazards, before working on the roof.
- Ladder safety training: setup, angle, tie-off, and 3 points of contact.
- A competent person on site to inspect fall protection, the deck, and site conditions.
- Heat illness prevention: signs, water and rest, and how to get help.
- Safe use of nail guns and circular saws, including GFCI use.
Emergency
If someone falls: stop all work, call 911 and give the full site address, and do not move the injured person unless they are in danger. If a worker is hanging in a harness, get them down within minutes using the ladder or rescue plan. Give first aid and send someone to the street to guide EMS in.
Official sources
- 29 CFR 1926.501 — Duty to have fall protectionecfr.gov
- 29 CFR 1926.502 — Fall protection systems criteria and practicesecfr.gov
- 29 CFR 1926.503 — Fall protection training requirementsecfr.gov
- 29 CFR 1926.1053 — Laddersecfr.gov
- 29 CFR 1926.25 — Housekeepingecfr.gov
- 29 CFR 1926.416 — Electrical — general requirementsecfr.gov
- 29 CFR 1926.102 — Eye and face protectionecfr.gov
- OSHA — Heat — hazard recognition and preventionosha.gov
Make this JHA for your own job
Describe the task and the site. You get a JHA like this on your letterhead, in English and Spanish, with a crew sign-off sheet — preview free.
General information, not legal advice. Templates and examples should be reviewed by a competent person before use. HardHat Binder is not affiliated with or endorsed by OSHA.